The Macon Water Authority has completed two improvement projects at the Amerson Water Treatment Plant Administration Building, with both projects finishing below their approved budgets.
The fountain refurbishment included resurfacing the existing water feature with a new membrane liner, installing new lighting, replacing two pumps and relocating pump equipment above ground for safer access. The project cost $53,231, compared with a budget of $110,000.


Inside the administration building, crews replaced damaged ceiling tiles and carpet, installed vinyl tile flooring, repaired walls and painted interior areas. That project cost $113,607, compared with a budget of $250,000.
Together, the projects cost $166,838 against combined budgets of $360,000, coming in $193,162 below budget.
The improvements were completed this year.